Most kitchen remodels that go wrong do not go wrong during construction. They go wrong in the three weeks before it, in decisions that seemed small at the time.

These are the ones we see most often from homeowners across Baton Rouge, Lafayette and Lake Charles.

1. Ordering countertops before the cabinets are in

This is the most expensive sequencing mistake, and it happens because people want to save time.

Countertops are templated — measured precisely against your actual installed cabinets. Not from a drawing, not from the old countertop. Cabinets settle, floors are rarely level, and a run that measures 96 inches on paper can measure 95 and a half once it is in.

A slab cut to a drawing that does not match the room is scrap. Set the cabinets, level them, then template.

2. Choosing the slab from a photograph

With quartz this is low risk, because it is manufactured to be consistent. With granite, marble or quartzite it is a genuine gamble.

Natural stone varies slab to slab from the same quarry, sometimes dramatically. The sample chip in a showroom is one small area of one slab. Veining, movement and background color can all differ from what arrives.

Walk the slab yard. Look at the whole piece. If you are buying natural stone, this is not an optional step.

3. Underestimating what humidity does to cheap cabinet boxes

This one is specific to where we live.

The cheapest ready-to-assemble cabinets use particleboard boxes. In a dry climate, they last acceptably. In a Baton Rouge kitchen — humidity year round, dishwasher steam, the occasional leak under the sink — the edges swell and the boxes fail from the bottom up.

The door is what you look at. The box is what holds up. Birch or plywood boxes cost more up front and are the difference between cabinets that last five years and cabinets that last twenty. See the cabinet range.

4. Forgetting that the countertop is not the whole cost

A quote per square foot is for the stone. A finished kitchen also involves:

  • Tear-out and disposal of the existing countertop
  • Sink and cooktop cutouts
  • Plumbing disconnection and reconnection
  • The sink itself, if you are changing it
  • Backsplash, which usually goes in after the countertop
  • Edge profile, if you want something beyond a straight edge

None of these are hidden charges. They are simply not always in the first number you are quoted. Ask what is included, and compare like with like. We break this down fully in the Baton Rouge countertop cost guide.

5. Designing the layout around the appliances you already own

Appliance dimensions are not standard in the way people assume, particularly for refrigerators and ranges. Building a cabinet run around a refrigerator you plan to replace in two years is a common way to end up with a gap you cannot fill.

Decide on appliances early — even if you are not buying them yet — and design to their specifications rather than to what is currently in the room.

6. Skipping ventilation

A kitchen in this climate needs to move air. Cooking puts moisture into a room that is already humid, and it has to go somewhere. Without a working extractor vented outside, it settles on cabinet doors, in the seam behind the countertop, and eventually in the caulk line where mold takes hold.

A recirculating hood that filters and returns air to the room is better than nothing and considerably worse than a vented one. If the wall run is possible, take it.

7. Treating the backsplash seam as an afterthought

The joint between countertop and backsplash is where kitchens fail first. It is a caulk line, not a permanent seal, and it moves as the house does.

Caulk it properly at install, inspect it once a year, and re-caulk when it starts to separate. Water getting behind a countertop into a cabinet box is one of the most common and most avoidable problems we see.

A sensible order of operations

  1. Settle the layout, including appliance dimensions
  2. Choose cabinets, then countertop material
  3. Walk the slab yard if you are buying natural stone
  4. Install and level cabinets
  5. Template countertops against the installed cabinets
  6. Fabricate and install
  7. Backsplash, then caulk
  8. Plumbing reconnection

The step people want to compress is between four and five. It is the one that cannot be compressed.

Frequently asked questions

How long does a kitchen remodel take in Baton Rouge?

It depends on scope and on lead times when you order. The fixed constraint is that countertops cannot be templated until cabinets are set, and fabrication takes time after templating. Ask your supplier for current lead times when you get your quote.

Should I stay in the house during a kitchen remodel?

Most people do. Set up a temporary sink and microwave elsewhere before work starts — the kitchen will be unusable for longer than you expect, especially between countertop template and install.

Do I need a permit for a kitchen remodel?

Cosmetic replacement generally does not. Moving plumbing, gas or electrical usually does. Check with East Baton Rouge Parish before work starts rather than after.

Is it worth remodeling the kitchen before selling?

A dated kitchen is one of the most common reasons buyers discount an offer. Replacing failed countertops and tired cabinet doors usually returns more than a full gut renovation does, if selling is the goal.

Plan it properly

If you are at the stage of sketching layouts, bring the sketch in. Getting the sequence right at the start costs nothing and saves the most.

Baton Rouge showroom: 5251 S Sherwood Forest Blvd, (225) 239-5816. Browse recent local projects or get in touch.

Samuel

Samuel writes about countertops, cabinets and kitchen remodeling for EE Kitchen & Bath, serving homeowners and contractors across Baton Rouge, Lafayette and Lake Charles, Louisiana.

View all posts

Leave a Reply

Your email address will not be published. Required fields are marked *